| Step 1 - The (2-3 man) crew will arrive at your home and start the ground preparation. First, the ground will be marked with spray paint or a string line. Then a small sod cutter is used to remove the grass where the curb is to be installed. This process will NOT disturb existing beds. | ![]() |
| Step 2 - Concrete is mixed with color additives on site using a small mixer mounted on our trailer. There will be no heavy equipment or concrete trucks on your property. | ![]() |
| Step 3 - The concrete is fed into the extruder from a wheelbarrow. This creates the shape of the continuous concrete curb. | ![]() |
| Step 4 - The curb is then hand-finished using a trowel and special stamping tools. | ![]() |
| Step 5 - Control/Expansion joints are cut approximately every 3 feet while the concrete is wet. The cut is approximately 1/3 of the way through the curb. This is to minimize cracking. | ![]() |